UST Headquarters Fitout

Previous Next

project at a glance

The 21-week ultra fast-track construction phase of the UST Headquarters project included a 120,000 square foot fit-out of office space in three connected buildings. The project involved extensive coordination with the landlord, who was completing base building upgrades to the atrium and MEP systems in parallel with the start of the fit-out.

Turner was engaged from the start of design in order to provide the Owner and Architect with budget, cost and schedule impact information. In the three-month preconstruction phase, Turner also provided pre-purchasing services for large electrical equipment such as GenSets, uninterruptible power supplies (UPS) and automatic transfer switches (ATS) to meet a fast-track room-ready date for the data center.

 