Internap Data Center

Previous Next

project at a glance

The Internap Data Center fit-out included 35,000 square feet of renovations to architectural, as well as all supporting electrical, mechanical and fire protection infrastructure. Electrical upgrades included removal and installation of switchgear, automatic transfer switches, paralleling gear and power distribution panels. Batteries and a corresponding uninterruptible power system were also installed. To meet Internap's goal of LEED Certification, the project team employed sustainable building practices such as the resuse of existing building materials, energy savings and management of indoor air quality. To meet this project's highly accelerated schedule, the project team worked seven days a week for two months, and a second shift was added at the peak of construction.

Turner International

For Services / Specializations
and Additional Key Contacts
See Office Network

*Office includes a Special
Projects Division or Interiors
Group