Headquarters
Turner Construction Company
66 Hudson Boulevard East
New York, NY 10001
(212) 229-6000 turner@tcco.comEthics & Compliance Hotline
Report issues 24 hours a day, 7 days a week to Turner’s Confidential Reporting System
(888) 738-1924 https://turnerconstruction.ethicspoint.comSubcontractors
Before reaching out, please review our prequalification requirements.
Become a Subcontractor2020
U.S. Army Corps of Engineers
Government/Public
Interiors
24,000 sq. ft., 2-Stories
ESa (Earl Swensson Associates, Inc.)
The Nashville General Hospital at Meharry COVID-19 Acute-Care Facility project included a 24,000-sq. ft., fast-tracked renovation of two hospital floors into a COVID-19 acute-care facility. Due to the rapid spread of COVID-19, completion of this facility was urgent.
Turner managed a complex schedule of 24/7 work involving three eight-hour trade shifts per day, with overlapping jobs completed simultaneously. Turner delivered the project one day ahead of schedule, finishing a project normally taking six months in just 27 days.
Turner demolished 15,000 sq. ft. of unused storage space on the hospital’s eighth floor to house 40 new beds in single-patient rooms separated by partitions.
Turner created negative-pressure air space for these and 24 additional existing beds on the hospital's second floor and installed a new heating, ventilation, and air-conditioning system to support the hospital’s COVID-19 treatment rooms.