Amgen Data / Server Room

Previous Next

project at a glance

Work on the Amgen Data/Server Room included MEP upgrades to two 1,000 square foot data centers. Work also included removal and reinstallation of uninterruptible power supply equipment to provide redundancy and installation and reconfiguration of HVAC equipment to provide redundancy. Turner worked with Amgen’s commissioning agent to create the commissioning plan and sequence of operations and managed the commissioning process. The construction work was completed during a three-week manufacturing shutdown.