Turner provided general contracting services for the data center - the permanent feeder replacement of existing conductors in the underground duct banks from the electrical yard to the electrical support rooms. It addresses the eight primary and 14 remaining feeders in Bay 1 and the entire 22 feeders in Bay 2. Work included the building of a permanent overhead structural steel system and conduit route into the electrical rooms, improved concrete slab and reinforcement to meet structural and seismic requirements and replacement of remaining damaged switchgear.