Dean Foods

project at a glance

Raw & Pasteurized Milk Alcove Building Additions:  Building additions including facilities mechanical and electrical work to support raw and pasteurized milk processing equipment. Site utility modifications, exterior process foundations and raw and pasteurized milk storage tank rigging/setting work was also performed.

Freezer/Cooler Area Modifications: Selective building demolition, process equipment foundations, floor slab replacement, facilities mechanical and electrical modifications to allow installation of an automated dairy product storage system.

Finished Goods Conveyor Structures: Selective demolition, building addition, interior conveyor bridge foundations and structural steel, hydraulic piping and facilities mechanical and electrical work to support installation of a plant wide finished goods conveyor system.

For Services / Specializations
and Additional Key Contacts
See Office Network

*Office includes a Special
Projects Division or Interiors